Parking Lot and Steam System Construction Update
There will be construction on campus throughout the summer at various sites on campus.
In an attempt to reduce impacts to the campus during regularly scheduled classes, 色情视频鈥檚 Project Management Office has launched an aggressive schedule of improvement projects this summer.
These projects include several renovation projects within buildings; major excavations to do steam utility infrastructure repairs between Love Library and Hepner Hall and the ; and repairs to and .
The X-Lot was closed late May and will remain closed through June.
The top levels (5 and 6) of Parking Structure 2, located near the , were also closed on May 20 and will remain closed through June.
The entry at level 4 on Lindo Paseo Drive will be closed due to the one way traffic flow of the structure. The exit on level 4 will remain open. The remaining entry at level 1 on Hardy Avenue will be open for all entry in to the structure. Pedestrian traffic on levels 5 and 6 and through the structure will also be impeded.
Traffic control
Additional interruptions to campus traffic flow should be anticipated in the GMCS, and Facilities Services building areas. This is due to Phase 3 of the Steam Utilities Infrastructure Replacement Project which is now underway. This project is critical to maintaining the main steam distribution system responsible for heating the campus. Additional information about the Steam Utility Infrastructure Repairs Projects can be found .
This phase of construction is expected to run through August 2014. Between 6 a.m. and 6 p.m. a one lane road will be maintained and traffic will be controlled by flagmen.
From 6 p.m. to 6 a.m. there will be no flagmen and the single-lane will be available for one-way southbound traffic only.
For more information on construction activities on campus contact the Work Control Center via e-mail or call 619-594-4754.